The cutting and recovery operation, which included a net guard and the subsea wellhead, was performed from the subsea contruction vessel Olympic Zeus and marks a new world record for water depth with the Internal Multistring Cutting Tool (IMCT). The cut was made 5 meters below the seabed as per NORSOK guidelines and actual time spent on site was less than 26 hours despite up to 6 meters heave during the operation.
NCA's scope of work on the project was;
- project management
- engineering and preparation of work program
- facilitate hazop
- mobilisation of vessel, cutting and recovery equipment
- offshore removal of net guard and subsea wellhead
- "as left" survey
- demobilisation
For more information, please contact an NCA sales representative or project manager Øystein Kanestrøm (oka@nca-group.com / +47 51 64 91 60).